Gantt scheduling and dependencies
Documented in Gantt.
Gantt scheduling and dependencies
A warehouse fit-out on mapped fields with finish-to-start, start-to-start and finish-to-finish links with lags, the critical path and total float, auto and manual task modes, a constraint, an unscheduled task, the conflict dialog, project dates, durations, WBS codes and serial numbers.
- Drag a task before its predecessor or press a button
Demo.tsx
'use client';
import { useRef, useState } from 'react';
import { Gantt, type GanttApi, type GanttProps, type GanttTaskMode } from '@salmonui/gantt';
import { Button } from '@salmonui/buttons/button';
import { Checkbox } from '@salmonui/inputs/checkbox';
import { Select } from '@salmonui/dropdowns/select';
// Your own property names, mapped through taskFields.
type Task = {
TaskID: number;
Name: string;
Parent: number | null;
Begin?: string;
Days?: number;
Done?: number;
Deps?: string;
Manual?: boolean;
Constraint?: string;
ConstraintOn?: string;
};
const tasks: Task[] = [
{ TaskID: 1, Name: 'Warehouse fit-out', Parent: null },
{ TaskID: 2, Name: 'Permits', Parent: 1, Begin: '2027-04-05', Days: 5, Done: 100 },
{ TaskID: 3, Name: 'Demolition', Parent: 1, Days: 3, Done: 40, Deps: '2FS' },
{ TaskID: 4, Name: 'Electrical', Parent: 1, Days: 6, Deps: '3FS+2d' },
{ TaskID: 5, Name: 'Plumbing', Parent: 1, Days: 4, Deps: '3SS+1d' },
{ TaskID: 6, Name: 'Inspection (start no earlier than 26 Apr)', Parent: 1, Days: 1, Deps: '4FS,5FF', Constraint: 'startNoEarlierThan', ConstraintOn: '2027-04-26' },
{ TaskID: 7, Name: 'Racking (manual dates)', Parent: 1, Begin: '2027-04-19', Days: 3, Manual: true, Deps: '3FS' },
{ TaskID: 8, Name: 'Handover', Parent: 1, Days: 0, Deps: '6FS,7FS' },
{ TaskID: 9, Name: 'Signage (no dates yet)', Parent: 1 },
{ TaskID: 10, Name: 'Opening party (after the whole fit-out)', Parent: null, Days: 1, Deps: '1FS' },
];
const COLUMNS: NonNullable<GanttProps<Task>['columns']> = ['serialNumber', 'wbs', 'title', 'start', 'end', 'duration', 'progress', 'predecessors', 'wbsPredecessors'];
/** Dependency types and lags, the critical path and total float, task modes, auto scheduling, constraints, unscheduled tasks, conflict validation, project dates, durations, WBS and serial numbers on mapped fields. */
export default function GanttSchedulingDemo() {
const apiRef = useRef<GanttApi<Task>>(null);
const [data, setData] = useState<readonly Task[]>(tasks);
const [critical, setCritical] = useState(true);
const [auto, setAuto] = useState(true);
const [mode, setMode] = useState<GanttTaskMode>('custom');
const [validateManual, setValidateManual] = useState(false);
const [askConflicts, setAskConflicts] = useState(true);
const [log, setLog] = useState<string[]>([]);
const add = (line: string) => setLog((lines) => [line, ...lines].slice(0, 8));
return (
<div>
<div className="demo-toolbar">
<Checkbox checked={critical} onCheckedChange={(checked) => setCritical(checked)}>
Critical path
</Checkbox>
<Checkbox checked={auto} onCheckedChange={(checked) => setAuto(checked)}>
Auto schedule
</Checkbox>
<label>
Task mode
<Select aria-label="Task mode" data={[{ value: 'custom', label: 'custom (per-task Manual field)' }, { value: 'auto', label: 'auto' }, { value: 'manual', label: 'manual' }]} value={mode} onValueChange={(value) => value != null && setMode(value as GanttTaskMode)} />
</label>
<Checkbox checked={validateManual} onCheckedChange={(checked) => setValidateManual(checked)}>
Validate manual successors
</Checkbox>
<Checkbox checked={askConflicts} onCheckedChange={(checked) => setAskConflicts(checked)}>
Conflict dialog (else move the task)
</Checkbox>
</div>
<div className="demo-toolbar">
<Button variant="outline" type="button" onClick={() => add(`getCriticalTasks(): ${(apiRef.current?.getCriticalTasks() ?? []).map((t) => t.Name).join(', ')}`)}>
getCriticalTasks()
</Button>
<Button variant="outline"
type="button"
onClick={() => {
const i = apiRef.current?.getTaskInfo('5');
add(i ? `getTaskInfo(5): ${i.start?.toISOString().slice(0, 10)} to ${i.end?.toISOString().slice(0, 10)}, float ${i.totalFloat} h, WBS ${i.wbs}, ${apiRef.current?.formatDuration('5')}` : 'no task');
}}
>
getTaskInfo(5)
</Button>
<Button variant="outline" type="button" onClick={() => add(`setTaskMode(3, 'manual'): ${apiRef.current?.setTaskMode('3', 'manual').status}`)}>
setTaskMode(3, manual)
</Button>
<Button variant="outline" type="button" onClick={() => apiRef.current?.setProjectDates('2027-03-29', '2027-05-28')}>
setProjectDates
</Button>
<Button variant="outline" type="button" onClick={() => add(`updateTask(2, 8 days): ${apiRef.current?.updateTask('2', { Days: 8 }).status}`)}>
Permits take 8 days
</Button>
</div>
<Gantt<Task>
ref={apiRef}
aria-label="Warehouse fit-out schedule"
data={data}
taskFields={{ id: 'TaskID', title: 'Name', parentId: 'Parent', start: 'Begin', duration: 'Days', progress: 'Done', predecessors: 'Deps', manual: 'Manual', constraintType: 'Constraint', constraintDate: 'ConstraintOn' }}
columns={COLUMNS}
wbs={{ autoUpdate: true }}
timeZone="UTC"
locale="en-GB"
projectStart="2027-04-05"
height={500}
criticalPath={critical}
autoSchedule={auto}
taskMode={mode}
unscheduledTasks
validateDependencies
validateManualTasks={validateManual}
parentDependencies
dependencyLag={{ normalizeOnLoad: true, updateOnTaskbarEdit: true }}
connectorWidth={2}
onScheduleConflict={(e) => {
add(`onScheduleConflict: ${e.conflicts.map((c) => (c.task ? c.task.Name : '?')).join(', ')}`);
if (!askConflicts) e.resolve('move');
}}
onDataChange={(rows) => setData(rows)}
/>
<div className="demo-log" aria-live="polite">
<ol>{log.length ? log.map((line, i) => <li key={`${i}-${line}`}>{line}</li>) : <li>Drag a task before its predecessor or press a button</li>}</ol>
</div>
</div>
);
}
The rows use TaskID, Name, Parent, Begin, Days, Done, Deps,
Manual, Constraint and ConstraintOn; taskFields maps them. Only
Permits has a start: every other date is derived from the links (2FS,
3FS+2d, 3SS+1d, 4FS,5FF) on working days, and the parent bar rolls
up its children. The inspection cannot start before 26 April
(startNoEarlierThan). Critical bars and connectors are marked; untick
"Critical path" to hide them. The opening party links to the parent task itself
(parentDependencies). Drag Plumbing two days later: its 3SS+1d lag
becomes 3SS+3d (dependencyLag.updateOnTaskbarEdit). Racking has manual dates (task mode
custom with the Manual field); with "Validate manual successors" its
link moves it too. Signage has no dates and is drawn as an unscheduled
placeholder. Drag Electrical before the end of Demolition: the conflict
dialog offers to move the task, remove the link or cancel (untick
"Conflict dialog" to move it at once through onScheduleConflict). Untick
"Auto schedule" to keep the data dates. The serial number, WBS and WBS
predecessor columns are presets.